Glossary of Project Management Terms & Descriptions
[Common
Acronyms] [Definitions]
COMMON ACRONYMS
AC - Actual Cost
ACWP - Actual Cost of Work Performed
AD - Activity Description
ADM - Arrow Diagramming Method
AF - Actual Finish date
AOA - Activity-on-Arrow
AON - Activity-on-Node
AS - Actual Start date BAG: Budget at Completion
BCWP - Budgeted Cost of Work Performed
BCWS - Budgeted Cost of Work Scheduled
CAP - Control Account Plan (previously called Cost Account Plan)
CCB - Change Control Board
CPFF - Cost-Plus-Fixed-Fee
CPI - Cost Performance Index
CPIF - Cost-Plus-Incentive-Fee
CPM - Critical Path Method
CV - Cost Variance
DD - Data Date
DU - Duration
EAC - Estimate at Completion
EF - Early Finish date
ES - Early Start date
ETC - Estimate to Complete
EV - Earned Value
EVM - Earned Value Management
FF - Free Float or Finish-to-Finish
FFP - Firm Fixed-Price
FRF - Fixed-Price- Incentive- Fee
FS - Finish 40-Start
GERT - Graphical Evaluation and Review Technique
IFB - Invitation for Bid
LF - Late Finish date
LOE - Level of Effort
LS - Late Start date
OBS - organisation (al) Breakdown Structure
PC - Percent Complete
PDM - Precedence Diagramming Method
PERT - Program Evaluation and Review Technique
PF - Planned Finish date
PM - Project Management or Project Manager
PMBOK - Project Management Body of Knowledge
PMP - Project Management Professional
PS - Planned Start date
PV - Planned Value
QA - Quality Assurance
QC - Quality Control
RAM - Responsibility Assignment Matrix
RDU - Remaining Duration
RFP - Request for Proposal
RFQ - Request for Quotation
SF - Scheduled Finish date or Start-to-Finish
SOW - Statement of Work
SPI - Schedule Performance Index
SS - Scheduled Start date or Start-to-Start
SV - Schedule Variance
TC - Target Completion date
TF - Total Float or Target Finish date
TQM: Total Quality Management
TS: Target Start date
VE: Value Engineering
WBS: Work Breakdown Structure
DEFINITIONS Many of the words defined here have broader and
in some cases different, dictionary definitions.
The definitions use the following conventions:
-
Terms used as part of the definitions and that are defined in the glossary
are shown in italics.
- When synonyms are included, no definition is given and the reader is directed
to the preferred term (i.e., see preferred term).
- Related terms that are not synonyms are cross-referenced at the end of
the definition (i.e., see also related term).
A
Accountability Matrix: See responsibility assignment
matrix.
Activity: An element of work performed during
the course of a p-. An activity normally has an expected duration, an
expected cost, and expected resource requirement. Activities can be subdivided
into tasks.
Activity Definition: Identifying the specific
activities that must be performed to produce the various project deliverables.
Activity Description (AD): A short phrase or label
used in a Project network diagram. The activity description normally describes
the Scope of work of the activity.
Activity Duration Estimating: Estimating the number
of work periods that will be needed to complete individual activity.
Activity-on-Arrow (AOA): See arrow-diagramming
method.
Activity-on-Node (AON): See precedence diagramming
method.
Activity Sequencing: Identifying and documenting
interactivity logical relationships.
Actual Cost (AC): Total costs incurred that must
relate to whatever cost was budgeted within the planning value and earned
value (which can sometimes be direct labor hours alone, direct costs alone,
or all costs including indirect costs) in accomplishing work during a
given time period. See also earned value.
Actual Cost of Work Performed (ACWP): This term
has been replaced with the term actual cost.
Actual Finish Date (AF): The point in time that
work actually ended on an activity. (Note: In some application area, the
activity is considered "finished" when work is substantially
complete.")
Actual Start Date (AS): The point in time that
work actually started on an activity.
Administrative Closure: Generating, gathering,
and disseminating information to formaliz phase or project completion.
Application Area: A category of projects that
have common elements not present in all projects. Application areas are
usually defined in terms of either the product of the project (i.e., by
similar technologies or industry sectors) or the type of customer (e.g.,
internal versus external, government versus commercial). Application areas
often overlap.
Arrow: The graphic presentation of an activity.
See also arrow-diagramming method.
Arrow Diagramming Method (ADM): A network diagramming
technique in which activities are represented by arrows. The tail of the
arrow represents the start, and the head represents the finish of the
activity (the length of the arrow does not represent the expected duration
of the activity). Activities are connected at points called nodes (usually
drawn as small circles) to illustrate the sequence in which the activities
are expected to be performed. See also precedence diagramming method.
As-of Date: See 'data 'date.
Assumptions: Assumptions are factors that, for
planning purposes, are considered to be true, real, or certain. Assumptions
affect all aspects of project planning, and are part of the progressive
elaboration of the project. Project teams frequently identify, document,
and validate assumptions as part of their planning process. Assumptions
generally involve a degree of risk.
Assumptions analysis: A technique that explores
the assumptions' accuracy and identifies risk to the project from inaccuracy,
inconsistency, or incompleteness of assumptions.
B
Backward Pass: The calculation of late finish
dates and late start dates for the uncompleted portions of all network
activities. Determined by working backwards through the network logic
from the project’s end date. The end date may be calculated in a
forward pass or set by the customer or sponsor. See also network analysis.
Bar Chart: A graphic display of schedule-related
information. In the typical bar chart, activities or other project elements
are listed down the left side of the chart, dates are shown across the
top, and activity durations are shown as date-placed horizontal bars.
Also called a Gantt chart.
Baseline: The original approved plan (for project,
a work package, or an activity), plus or minus approved scope changes
Usually used with a modifier (e g, cost baseline, schedule baseline, performance
measurement baseline).
Baseline Finish Date: See schedule finish date.
Baseline Start Date: See schedule start date.
Brainstorming: A general creativity technique
that can be used to identify risk using a group of team members or subject-matter
experts. Typically, a brainstorming session is structured so that each
participant's ideas are recorded for later analysis. A tool of the risk
identification process.
Budget at Completion (BAC): The sum of the total
budgets for a project.
Budget Estimate: See estimate.
Budgeted Cost of Work Performed (BCWP): This term
has been replaced with the term earned value.
Budgeted Cost of Work Scheduled (BCWS): This term
has been replaced with the term
planned value.
Buffer: See reserve.
C
Calendar Unit: The smallest unit of time used
in scheduling the project. Calendar units are generally in hours, days,
or weeks, but can also be in shifts or even in minutes. Used primally
in relation to project management software.
Change Control Beard (CCB): A formally constituted
group of stakeholders responsible for approving or rejecting changes to
the project baselines.
Chart of Accounts: Any numbering System used to
monitor project costs by category (e.g., labor, supplies, materials, and
equipment). The project chart of accounts is usually based upon the corporate
chart of accounts of the primary performing organisation. See also code
of accounts.
Charter: See project charter.
Checklist: A listing of many possible risks that
might occur on a project. It is used as a tool in the risk identification
process. Checklists are comprehensive, listing several types of risk that
have been encountered on prior projects.
Code of Accounts: Any numbering system used to
uniquely identify each element of the work breakdown structure. See also
chart of accounts.
Communications Planning: Determining the information
and communications needs of the project stakeholders: who needs what information,
when they will need it, and how it will be given to them.
Component: A constituent part, an element.
Constraint: Applicable restriction that will affect
the performance of the project. Any factor that affects when an activity
can be scheduled.
Contingencies: See reserve and contingency planning.
Contingency Allowance: See reserve.
Contingency Planning: The development of a management
plan that identifies alternative strategies to be used to ensure project
success if specified risk events occur.
Contingency Reserve: The amount of money or time
needed above the estimate to reduce the risk of overruns of project objectives
to a level acceptable to the organisation.
Contract: A contract is a mutually binding agreement
that obligates the seller to provide the specified product and obligates
the buyer to pay for it Contracts generally fall into one of three broad
categories:
·
Fixed-price or lump-sum contracts--this category of contract involves
a fixed total price for a well-defined product. Fixed-price contracts
may also include incentives for meeting or exceeding selected project
objectives, such as schedule targets.
·
Cost-reimbursable contract--this category of contract involves payment
(reimbursement) to the contractor for its actual costs. Costs are usually
classified as direct costs (costs incurred directly by the project, such
as wages for members of the project team) and indirect costs (costs allocated
to the project by the per-forming organisation as a cost of doing business,
such as salaries for corporate executives). Indirect costs are usually
calculated as a percentage of direct costs. Cost-reimbursable contracts
often include incentives for meeting or exceeding selected project objectives,
such as schedule targets or total cost.
·
Time and material contracts--time and material contracts are a hybrid
type of contractual arrangement that contain aspects of both cost-reimbursable
and fixed-price-type arrangements. Time and material contracts resemble
cost-type arrangements in that they are open ended, because the full
value of the arrangement is not defined at the time of the award. Thus,
time and material contracts can grow in contract value as if they were
cost-reimbursable-type arrangements. Conversely, time and material arrangements
can also resemble fixed-unit arrangements when, for example, the unit
rates are preset by the buyer and seller, as when both parties agree
on the rates for the category of ~senior engineers."
Contract Administration: Managing the relationship
with the seller.
Contract Closeout: Completion and settlement of
the contract, including resolution of any open items.
Control: The process of comparing actual performance
with planned performance, analyzing variances, evaluating possible alternatives,
and taking appropriate corrective action as needed.
Control Account Plan (CAP): Previously called
a Cost Account Plan. The CAP is a management control point where the
integration of scope and budget and schedule takes place, and where the
measurement of performance will happen. CAPs are placed at selected management
points of the work breakdown structure.
Control Charts: Control charts are a graphic display
of the results, over time and against established control limits, of a
process. They are used to determine if the process is ~in control"
or in need of adjustment.
Corrective Action: Changes made to bring expected
future performance of the project in line with the plan.
Cost Budgeting: Allocating the cost estimates
to individual work activities.
Cost Control: Controlling changes to the project
budget.
Cost Estimating: Developing an approximation (estimate)
of the cost of the resources needed to complete project activities.
Cost of Quality: The costs incurred to ensure
quality. The cost of quality includes quality
Planning, quality control, quality assurance,
and rework.
Cost Performance Index (CPI): The cost efficiency
ratio of earned value to actual costs.
CPI is often used to predict the magnitude of
a possible cost overrun using the following formula: BAC/CPI = projected
cost at completion. CPI = EV divided by AC.
Cost-Plus-Fixed-Fee (CPFF) Contract: A type of
contract where the buyer reimburses the seller for the seller's allowable
costs (allowable costs are defined by the contract) plus a fixed amount
of profit (fee).
Cost-Plus-Incentive-Fee (CPIF) Contract: A type
contract where the buyer reimburses the seller for the seller's allowable
costs (allowable costs are defined by the contract), and the seller earns
its profit if it meets defined performance criteria.
Cost Variance (CV): 1) Any difference between
the budgeted cost of an activity and the actual cost of that activity.
2) In earned value, EV less ACWP = CV.
Crashing: Taking action to decrease the total
project duration after analyzing a number of alternatives to determine
how to get the maximum duration compression for the least cost.
Critical Activity: Any activity on a critical
path. Most commonly determined by using the critical path method Although
some activities are "critical," in the dictionary sense, without
being on the critical path this meaning is seldom used in the project
context.
Critical Path: The series of activities that
determines the duration of the project. In a deterministic model, the
critical path is usually defined as those activities with float less than
or equal to a specified value, often zero. It is the longest path through
the project. See critical path method.
Critical Path Method (CPM): A network analysis
technique used to predict project duration by analyzing which sequence
of activities (which path) has the least amount of scheduling flexibility
(the least amount of float). Early dates are calculated by means of a
forward pass, using a specified start date. Late dates are calculated
by means of a backward pass, starting from a specified completion date
(usually the forward pass' calculated project early finish date).
Current Finish Date: The current estimate of the
point in time when an activity will be completed.
Current Start Date: The current estimate of the
point in time when an activity will begin.
D
Data Date (DD): The date at which, or up to which,
the project's reporting system has provided actual status and accomplishments.
Also called as-of-date.
Decision Tree Analysis: The decision tree is a
diagram that describes a decision under consideration and the implications
of choosing one or another of the available alternatives. It incorporates
probabilities or risk and the costs or rewards of each logical path of
events and future decisions.
Definitive Estimate: See estimate.
Deliverable: Any measurable, tangible, verifiable
outcome, result, or item that must be produced to complete a project or
part of a project. Often used more narrowly in reference to an external
deliverable, which is a deliverable that is subject to approval by the
project sponsor or customer.
Dependency: See logical relationship.
Dummy Activity: An activity zero duration used
to show a logical relationship in the arrow diagramming method. Dummy
activities are used when logical relationships cannot be completely or
correctly described with regular activity arrows. Dummies are shown graphically
as a dashed line headed by an arrow.
Duration (DU): The number of work periods (not
including holidays or other nonworking periods) required to complete an
activity or other project element. Usually expressed as workdays or workweeks.
Sometimes incorrectly equated with elapsed time. See also effort.
Duration Compression: Shortening the project schedule
without reducing the project scope. Duration compression is not always
possible and often requires an increase in project cost.
E
Early Finish Date (EF): In the critical path method,
the earliest possible point in time on which the uncompleted portions
of an activity (or the project) can finish, based on the network logic
and any schedule constraints. Early finish dates can change as the project
progresses and changes are made to the project plan.
Early Start Date (ES): In the critical path method,
the earliest possible point in time on which the uncompleted portions
of an activity (or the project) can start, based on the network logic
and any schedule constraints. Early start dates can change as the project
progresses and changes are made to the project plan
Earned Value (EV): The physical work accomplished
plus the authorized budget for this work. The sum of the approved cost
estimates (may include overhead allocation) for activities (or portions
of activities) completed during a given period (usually project-to-date).
Previously called the budgeted cost of work performed (BCWP) for an activity
or group of activities.
Earned Value Management (EVM): A method for integrating
scope, schedule, and resources, and for measuring project performance.
It compares the amount of work that was planned with what was actually
earned with what was actually spent to determine if cost and schedule
performance are as planned.
Effort: The number of labor units required to
complete an activity, or other project element. Usually expressed as staff
hours, staff days, or staff weeks. Should not be confused with duration.
Element: One of the parts, substances, or principles
that make up a compound or complex whole.
Estimate: An assessment of the likely quantitative
result. Usually applied to project costs and durations and should always
include some indication of accuracy (e.g., +x percent). Usually used
with a modifier (e.g., preliminary, conceptual, feasibility). Some application
areas have specific modifiers that imply particular accuracy ranges (e.g.,
order-of-magnitude estimate, budget estimate, and definitive estimate
in engineering and construction projects).
Estimate at Completion (EAC): The expected total
cost of an activity, a group of activities, or the project when the defined
scope of work has been completed. Most techniques for forecasting EAC
include some adjustment of the original cost estimate, based on actual
project performance to date.
Estimate to Complete (ETC): The expected additional
cost needed to complete an activity, a group of activities, or the project.
Most techniques for forecasting ETC include some adjustment to the original
estimate, based on project performance to date. Also called estimated
to complete." See also earned value and estimate at completion.
Event-on-Node: A network diagramming technique
in which events are represented by boxes (or nodes) connected by arrow
to show the sequence in which the events are to occur Used in the original
program evaluation and review technique.
Exception Report: Document that includes only
major variations from plan (rather than all variations).
F
Fast Tracking: Compressing the project schedule
by overlapping activities that would normally be done in sequence, such
as design and construction.
Finish Date: A point in time associated with an
activity’s completion. Usually qualified by one of the following
actual, planned, estimated, scheduled, early, late, baseline, target,
or current.
Finish-to-Finish (FF): See logical relationship.
Finish-to-Start (FS): See logical relationship.
Firm Fixed-Price (FFP) Contract: A type of contract
where the buyer pays the seller a set amount (as defined by the contract),
regardless of the seller's costs.
Fixed-Price Contract. See firm fixed-price contract.
Fixed-Price-Incentive-Fee (FPIF) Contract: A type
of contract where the buyer pays the seller a set amount (as defined by
the contract), and the seller can earn an additional amount if it meets
defined performance criteria
Float: The amount of time that an activity may
be delayed from its early start without delaying the project finish date.
Float is a mathematical calculation, and can change as the project progresses
and changes are made to the project plan. Also called slack, total float,
and path float. See also free float.
Forecast Final Cost: See estimate at completion.
Forward Pass: The calculation of the early start
and early finish dates for the uncompleted portions of all network activities
See also network analysis and backward pass.
Fragnet: See subnet.
Free Float (FF): The amount of time that an activity
can be delayed without delaying the early start of any immediately following
activities See float.
Functional Manager: A manager responsible for
activity in a specialized department or function (e.g., engineering, manufacturing,
marketing).
Functional organisation: An organisation structure
in which staff are grouped hierarchically by specialty (e.g., production,
marketing, engineering, and accounting at the top level; with engineering,
further divided into mechanical, electrical, and others).
G
Gantt Chart. See bar chart.
Grade: A category or rank used to distinguish
items that have the same functional use (e.g., "hammer"), but
do not share the same requirements for quality (e.g., different hammers
may need to withstand different amounts of force).
Graphical Evaluation and Review Technique (GERT):
A network analysis technique that allows for conditional and probabilistic
treatment logical relationship (i.e., some activities may not be performed).
H
Hammock: An aggregate or summary activity (a group
of related activities is shown as one and reported at a summary level).
A hammock may or may not have an internal sequence. See also subproject
and subnet.
Hanger: An unintended break in a net work path.
Hangers are usually caused by missing activities or missing logical relationship.
I
Information Distribution: Making needed information
available to project stakeholders in a timely manner.
Initiation: Authorizing the project or phase.
Integrated Change Control: Coordinating changes
across the entire project.
Integrated Cost/Schedule Reporting: See earned
value.
Invitation for Bid (IFB): Generally, this term
is equivalent to request for proposal. However, in some application areas,
it may have a narrower or more specific meaning.
K
Key Event Schedule: See master schedule.
L
Lag: A modification of a logical relationship
that directs a delay in the successor task. For example, in a finish-to-start
dependency with a ten-day lag, the successor activity cannot start until
ten days after the predecessor has finished. See also lead.
Late Finish Date (LF): In the critical path method,
the latest possible point in time that an activity may be completed without
delaying a specified milestone (usually the project finish date).
Late Start Date (LS): In the critical path method,
the latest possible point in time that an activity may begin without delaying
a specified milestone (usually the finish date).
Lead: A modification of a logical relationship
that allows an acceleration of the successor task. For example, in a finish-to-start
dependency with a ten-day lead, the successor activity can start ten days
before the predecessor has finished. See also lag.
Lessons Learned: The learning gained from the
process of performing the project. Lessons learned may be identified at
any point. Also considered a project record.
Level of Effort (LOE): Support-type activity
(e.g., vendor or customer liaison) that does not readily lend itself to
measurement of discrete accomplishment. It is generally characterized
by a uniform rate of activity over a period of time determined by the
activities it supports.
Leveling: See resource leveling.
Life-Cycle Costing: The concept of including acquisition,
operating, and disposal costs when evaluating various alternatives.
Line Manager: 1) The manager of any group that
actually makes a product or performs a service. 2) A functional manager.
Link: See logical relationship.
Logic: See network logic.
Logic Diagram: See project network diagram.
Logical Relationship: A dependency between two
project activities, or between a project activity and a milestone. See
also precedence relationship. The four possible types of logical relationship
are:
·
Finish-to-start--the initiation of work of the successor depends upon
the completion of work of the predecessor.
·
Finish-to-finish--the completion of the work of the successor cannot finish
until the completion of work of the predecessor.
·
Start-to-start--the initiation of work of the successor depends upon the
initiation of the work of the predecessor.
·
Start-to-finish--the completion of the successor is dependent upon the
initiation of the predecessor.
Loop: A network path that passes the same node
twice. Loops cannot be analysed using traditional network analysis techniques
such as critical path method and program evaluation and review technique.
Loops are allowed in graphical evaluation and review technique.
M
Master Schedule: A summary-level schedule that
identifies the major activities and key milestone. See also milestone
schedule.
Mathematical Analysis: See network analysis.
Matrix organisation: Any organisational structure
in which the project manager shares responsibility with the functional
managers for assigning priorities and for directing the work of individuals
assigned to the project.
Milestone: A significant event in the project,
usually completion of a major deliverable.
Milestone Schedule: A summary-level schedule that
identifies the major milestone. See also master schedule.
Mitigation: See risk mitigation.
Monitoring: The capture, analysis, and reporting
of project performance, usually as compared to plan.
Monte Carlo Analysis: A technique that performs
a project simulation many times to calculate a distribution of likely
results. See simulation.
N
Near-Critical Activity: An activity that has
low total float.
Network. See project network diagram.
Network Analysis: The process of identifying early
and late start and finish dates for the uncompleted portions of project
activities See also critical path method, program evaluation and review
technique, and graphical evaluation and review technique.
Network Logic: The collection of activity dependencies
that makes up a project network.
Network Path: Any continuous series of
connected activities in a project network diagram.
Node: One of the defining points of a network;
a junction point joined to some or all of the other dependency lines.
See also arrow diagramming method and precedence diagramming method.
O
Order-of-Magnitude Estimate: See estimate.
organisational Breakdown Structure (OBS): A depiction
of the project organisation arranged so as to relate work packages to
organisational units.
organisational Planning: Identifying, documenting,
and assigning project roles, responsibilities, and reporting relationships.
Overlap: See lead.
P
Parametric Estimating: An estimating technique
that uses a statistical relationship between historical data and other
variables (e.g., square footage in construction, lines of code in software
development) to calculate an estimate.
Pareto Diagram: A histogram, ordered by frequency
of occurrence, that shows how many results were generated by each identified
cause.
Path: A set of sequentially connected activities
in a project network diagram.
Path Convergence: The node in the schedule where
parallel paths merge or join. At that node, delays or elongation or any
converging path can delay the project. In quantitative risk analysis of
a schedule, significant risk may occur at this point.
Path Float: See float.
Percent Complete (PC): An estimate, expressed
as a percent, of the amount of work that has been completed on an activity
or a group of activities.
Performance Measurement Baseline: An approved
plan against which deviations are compared for management control.
Performance Reporting: Collecting and disseminating
performance information. This includes status reporting, progress measurement,
and forecasting.
Performing organisation: The enterprise whose
employees are most directly involved in doing the work of the project.
PERT Chart: The term is commonly used to refer
to a project network diagram. See program evaluation and review technique
for the traditional definition of PERT.
Phase: See project phase.
Planned Finish Date (PF): See schedule finish
date.
Planned Start Date (PS): See scheduled start date.
Planned Value (PV): The physical work scheduled,
plus the authorized budget to accomplish the scheduled work. Previously,
this was called the budgeted costs for work scheduled (BCWS).
Precedence Diagramming Method (PDM): A network
diagramming technique in which activities are represented by boxes (or
nodes). Activities are linked by precedence relationships to show the
sequence in which the activities are to be performed.
Precedence Relationship: The term used in the
precedence diagramming method for a logical relationship. In current usage,
however; precedence relationship, logical relationship, and dependency
are widely used interchangeably, regardless of the diagramming method
in use.
Predecessor Activity: 1) In the arrow diagramming
method, the activity that enters a node. 2) In the precedence diagramming
method, the from" activity.
Probability and Impact Matrix: A common way to
determine whether a risk is considered low, moderate, or high by combining
the two dimensions of a risk, its probability of occurrence, and its impact
on objectives if it occurs.
Procurement Planning: Determining what to procure
and when.
Product Scope: The features and functions that
characterize a product or service.
Program: A group of related Projects managed in
a coordinated way. Programs usually include an element of ongoing work.
Program Evaluation and Review Technique (PERT):
An event-oriented network analysis technique used to estimate program
duration when there is uncertainty in the individual activity duration
estimates. PERT applies the critical path method using durations that
are computed by a weighted average of optimistic, pessimistic, and most
likely duration estimates. PERT computes the standard deviation of the
completion date from those of the path's activity durations. Also known
as the Method of Moments Analysis.
Project: A temporary endeavor undertaken to create
a unique product, service, or result.
Project Charter: A document issued by senior management
that formally authorizes the existence of a project. And it provides the
project manager with the authority to apply organisational resources to
project activities
Project Communications Management: A subset of
project management that includes the processes required to ensure timely
and appropriate generation, collection and dissemination, storage and
ultimate disposition of project information. It consists of communications
planning, information distribution, performance reporting, and administrative
closure.
Project Cost Management: A subset of project management
that includes the processes required to ensure that the project is completed
within the approved budget. It consists of resource planning, cost estimating,
cost budgeting, and cost control.
Project Human Resource Management: A subset of
project management that includes the processes required to make the most
effective use of the people involved with the project. It consists of
organisational planning, staff acquisition and team development.
Project Integration Management: A subset of project
management that includes the processes required to ensure that the various
elements of the project are properly coordinated. It consists of project
plan development, project plan execution, integrated change control.
Project Life Cycle: A collection of generally
sequential project phase whose name and number are determined by the control
needs of the organisation or organisations involved in the project.
Project Management (PM): The application of knowledge,
skills, tools, and techniques to project activities to meet the project
requirements.
Project Management Body of Knowledge (PMBOK):
An inclusive term that describes the sum of knowledge within the profession
of project management. As with other professions--such as law, medicine,
and accounting--the body of knowledge rests with the practitioners and
academics that apply and advance it. The PMBOK® includes proven, traditional
practices that are widely applied, as well as innovative and advanced
ones that have seen more limited use.
Project Management Professional (PM P®): An individual
certified as such by the Project Management Institute (PMI®).
Project Management Software: A class of computer
applications specifically designed to aid with planning and controlling
project costs and schedules.
Project Management Team: The members of the project
team who are directly involved in project management activities. On some
smaller projects, the project management team may include virtually all
of the project team members.
Project Manager (PM): The individual responsible
for managing a project.
Project Network Diagram: Any schematic display
of the logical relationship of project activities. Always drawn from left
to right to reflect project chronology. Often referred to as a PERT chart.
Project Phase: A collection of logically related
project activities, usually culminating in the completion of a major
deliverable.
Project Plan: A formal, approved document used
to guide both project execution and project control. The primary uses
of the project plan are to document planning assumptions and decisions,
facilitate communication among stakeholders, and document approved scope,
cost, and schedule baselines. A project plan may be summary or detailed.
Project Plan Development: Integrating and coordinating
all project plans to create a consistent, coherent document.
Project Plan Development: Carrying out the project
plan by performing the activities included therein.
Project Planning: The development and maintenance
of the project plan.
Project Procurement Management: A subset of project
management that includes the processes required to acquire goods and services
to attain project scope from outside the performing organisation. It consists
of procurement planning, solicitation, source selection, contract administration,
and contract closeout.
Project Quality Management: A subset of project
management that includes the processes required to ensure that the project
will satisfy the needs for which it was undertaken It consists of quality
planning, quality assurance, and quality control.
Project Risk Management: Risk management is the
systematic process of identifying, analyzing, and responding to project
risk. It includes maximizing the probability and consequences of positive
events and minimizing the probability and consequences of events adverse
to project objectives. It includes the processes of risk management planning,
risk identification, qualitative risk analysis, risk response planning,
and risk monitoring and control.
Project Schedule: The planned dates for performing
activities and the planned dates for meeting milestone.
Project Scope: The work that must be done to deliver
a product with the specified features and functions.
Project Scope Management: A subset of project
management that includes the processes required to ensure that the project
includes all of the work required, and only the work required, to complete
the project successfully It consists of initiation, scope planning, scope
definition, scope verification, and scope change control.
Project Team Members: The people who report either
directly or indirectly to the project manager.
Project Time Management: A subset of project management
that includes the processes required to ensure timely completion of the
project It consists of activity definition, activity duration estimating,
schedule development, and schedule control.
Projectized organisation: Any organisational structure
in which the project manager has full authority to assign priorities and
to direct the work of individuals assigned to the project.
Q
Qualitative Risk Analysis: Performing a qualitative
analysis of risks and conditions to prioritize their effects on project
objectives. It involves assessing the probability and impact of project
risk(s) and using methods such as the probability and impact matrix to
classify risks into categories of high, moderate, and low for prioritized
risk response planning.
Quantitative Risk Analysis: Measuring the probability
and consequences of risks and estimating their implications for project
objectives. Risks are characterized by probability distributions of possible
outcomes. This process uses quantitative techniques such as simulation
and decision tree analysis.
Quality Assurance (QA): 1) The process of evaluating
overall project performance on a regular basis to provide confidence that
the project will satisfy the relevant quality standards. 2) The organisational
unit that is assigned responsibility for quality assurance.
Quality Control (Qc): 1) The process of monitoring
specific project results to determine if they comply with relevant quality
standards and identifying ways to eliminate causes of unsatisfactory performance.
2) The organisational unit that is assigned responsibility for quality
control.
Quality Planning: Identifying which quality standards
are relevant to the project, and determining how to satisfy them.
R
Remaining Duration (RDU): The time needed to complete
an activity.
Request for Proposal (RFP): A type of bid document
used to solicit proposals from prospective sears of products or services.
In some application areas, it may have a narrower or more specific meaning.
Request for Quotation (RFQ): Generally, this term
is equivalent to request for proposal. However, in some application areas,
it may have a narrower or more specific meaning.
Reserve: A provision in the project plan to mitigate
cost and/or schedule risk. Often used with a modifier (e.g., management
reserve, contingency reserve) to provide further detail on what types
of risk are meant to be mitigated. The specific meaning of the modified
term varies by application area.
Residual Risk: A risk that remains after risk
responses have been implemented.
Resource Leveling: Any form of network analysis
in which scheduling decisions (start and finish dates) are driven by resource
management concerns (e.g., limited resource availability or difficult-to-manage
changes in resource levels).
Resource-Limited Schedule: A project schedule
whose start and finish dates reflect expected resource availability. The
final project schedule should always be resource limited.
Resource Planning: Determining what resources
(people, equipment, materials) are needed in what quantities to perform
project activities.
Responsibility Assignment Matrix (RAM): A structure
that relates the project organisation structure to the work breakdown
structure to help ensure that each element of the project's scope of work
is assigned to a responsible individual.
Responsibility Chart: See responsibility assignment
matrix.
Responsibility Matrix: See responsibility assignment
matrix.
Retain age: A portion of a contract payment that
is held until contract completion to ensure full performance of the contract
terms.
Rework: Action taken to bring a defective or nonconforming
item into compliance with requirements or specifications.
Risk: An uncertain event or condition that, if
it occurs, has a positive or negative effect on a project's objectives.
Risk Acceptance: This technique of the risk response
planning process indicates that the project team has decided not to change
the p- plan to deal with a risk, or is unable to identify any other suitable
response strategy.
Risk Avoidance: Risk avoidance is changing the
project plan to eliminate the risk or to protect the project objectives
from its impact It is a tool of the risk response planning.
Risk Category: A source of potential risk reflecting
technical, project management, organisational, or external sources.
Risk Database: A repository that provides for
collection, maintenance, and analysis of data gathered and used in the
risk management processes. A lessons-learned program uses a risk database.
This is an output of the risk monitoring and control process.
Risk Event: A discrete occurrence that may affect
the project for better or worse.
Risk Identification: Determining which risk might
affect the project and documenting their characteristics. Tools used include
brainstorming and checklists.
Risk Management Plan: Documents how the risk processes
will be carried out during the project. This is the output of risk management
planning.
Risk Management Planning: Deciding how to approach
and plan risk management activities for a project.
Risk Mitigation: Risk mitigation seeks to reduce
the probability and/or impact of a risk to below an acceptable threshold.
Risk Monitoring and Control: Monitoring residual
risks, identifying new risks, executing risk reduction plans, and evaluating
their effectiveness throughout the project life cycle.
Risk Register: See risk response plan.
Risk Response Plan. A document detailing all identified
risk, including description, cause, probability of occurring, impact(s)
on objectives, proposed responses, owners, and current status. Also known
as risk register.
Risk Response Planning: Developing procedures
and techniques to enhance opportunities and reduce threats to the project's
objectives. The tools include avoidance, mitigation, transference, and
acceptance.
Risk Transference: Risk transference is seeking
to shift the impact of a risk to a third party together with ownership
of the response.
S
S-Curve: Graphic display of cumulative costs,
labor hours, percentage of work, or other quantities, plotted against
time. The name derives from the S-like shape of the curve (flatter at
the beginning and end, steeper in the middle) produced on a project that
starts slowly, accelerates, and then tails off. Also a term for the cumulative
likelihood distribution that is a result of a simulation, a tool quantitative
risk analysis.
Schedule: See project schedule.
Schedule Analysis: See network analysis.
Schedule Compression. See duration compression.
Schedule Control: Controlling changes to the project
schedule.
Schedule Development: Analyzing activity sequences,
activity durations, and resource requirements to create the project schedule.
Schedule Performance Index (SPI): The schedule
efficiency ratio of earned value accomplished against the planned value
The SPI describes what portion of the planned schedule was actually accomplished
The SPI = F" divided by PV.
Schedule Variance (SV): 1) Any difference between
the scheduled completion of an activity and the actual completion of that
activity. 2) In earned value, EV less BCWS = SV.
Scheduled Finish Date (SF): The point in time
that work was scheduled to finish on an activity. The scheduled finish
date is normally within the range of dates delimited by the early finish
date and the late finish date. It may reflect leveling or scarce resources.
Scheduled Start Date (SS): The point in time that
work was scheduled to start on an activity. The scheduled start date is
normally within the range of dates delimited by the early start date and
the late start date. It may reflect leveling of scarce resources.
Scope: The sum of the products and services to
be provided as a project. See project scope and product scope.
Scope Baseline: See baseline.
Scope Change: Any change to the project scope.
A scope change almost always requires an adjustment to the project cost
or schedule.
Scope Change Control: Controlling changes to project
scope.
Scope Definition: Subdividing the major deliverables
into smaller, more manageable components to provide better control.
Scope Planning: The process of progressively elaborating
the work of the project, which includes developing a written scope statement
that includes the project justification, the major deliverables, and the
project objectives..
Scope Statement: The scope statement provides
a documented basis for making future project decisions and for confirming
or developing common understanding of project scope among the stakeholders.
As the project progresses, the scope statement may need to be revised
or refined to reflect approved changes to the scope of the project.
Scope Verification: Formalizing acceptance of
the project scope.
Secondary Risk: A risk that arises as a direct
result of implementing a risk response.
Seller: The provider of goods or services to an
organisation.
Should-Cost Estimate: An estimate of the cost
of a product or service used to provide an assessment of the reasonableness
of a prospective contractor's proposed cost.
Simulation: A simulation uses a project model
that translates the uncertainties specified at a detailed level into their
potential impact on objectives that are expressed at the level of the
total project. Project simulations use computer models and estimates of
risk at a detailed level, and are typically performed using the Monte
Carlo technique.
Slack: Term used in arrow diagramming method for
float.
Solicitation: Obtaining quotations, bids, offers,
or proposals as appropriate.
Solicitation Planning: Documenting product requirements
and identifying potential sources.
Source Selection: Choosing from among potential
sellers.
Staff Acquisition: Getting needed human resources
assigned to and working on the project.
Stakeholder: Individuals and organisations that
are actively involved in the project, or whose interests may be positively
or negatively affected as a result of project execution or project completion.
They may also exert influence over the project and its results.
Start Date: A point in time associated with an
activity’s start, usually qualified by one of the following: actual,
planned, estimated, scheduled, early, late, target, baseline, or current.
Start-to-Finish (SF): See logical relationship.
Start-to-Start (SS): See logical relationship.
Statement of Work (SOW): A narrative description
of products or services to be supplied under contract.
Subnet. A subdivision of a project network diagram,
usually representing some form of sub-project.
Subnet work: See subnet.
Subproject: A smaller portion of the overall project.
Successor Activity: 1) In the arrow diagramming
method, the activity that departs a node. 2) In the precedence diagramming
method, the "to" activity.
T
Target Completion Date (TC): An imposed date that
constrains or otherwise modifies the network analysis.
Target Finish Date: (TF). The date that work is
planned (targeted) to finish on an activity.
Target Schedule: See baseline.
Target Start Date (TS): The date that work is
planned (targeted) to start on an activity
Task: A generic term for work that is not included
in the work breakdown structure, but potentially could be a further decomposition
of work by the individuals responsible for that work. Also, level of effort
on a project.
Team Development: Developing individual and group
competencies to enhance project performance.
Team Members: See project team members.
Technical Performance Measurement: Technical performance
measurement compares technical accomplishments during project execution
to the project plan's schedule of technical achievement.
Time-Scaled Network Diagram: Any project network
diagram drawn in such a way that the positioning and length of the activity
represent its duration. Essentially, it is a bar chart that includes network
logic.
Total Float (TF): See float.
Total Quality Management (TQM): A common approach
to implementing a quality improvement program within an organisation.
Transference: See risk transference.
Triggers: Triggers, sometimes called risk symptoms
or warning signs, are indications that a risk has occurred or is about
to occur. Triggers may be discovered in the risk identification process
and watched in the risk monitoring and control process.
V
Value Engineering (VE): Value 6ngineering is a
creative approach used to optimize life-cycle costs, save time, increase
profits, improve quality, expand market share, solve problems, and/or
use resources more effectively.
W
Workaround: A response to a negative risk event.
Distinguished from contingency plan in that a workaround is not planned
in advance of the occurrence of the risk event.
Work Breakdown Structure (WBS): A deliverable-oriented
grouping of project elements that organizes and defines the total work
scope of the project. Each descending level represents an increasingly
detailed definition of the project work.
Work Item: Term no longer in common usage. Synonymous
with activity—see activity.
Work Package: A deliverable at the lowest
level of the work breakdown structure, when that deliverable may be assigned
to another project manager to plan and execute This may be accomplished
through the use of a subproject where the work package may be further
decomposed into activities.
|